Skip to main content

User Prompt

“Write an RFI about the duct conflict with the beam at grid B-3 on level 2.”

Tool Call Sequence

1

Get the duct at grid B-3

Call: Query
Response:
2

Get the beam at grid B-3

Call: Query
Response:
What the agent learns so far: The duct bottom (10’-6”) is below the beam top (11’-2”) — they physically overlap by 8 inches. The agent has sheet references for both elements.
3

Check relevant general notes

Call: Query
Response:
What the agent learns: General Note 1 requires 2” clearance from structure. The duct-beam overlap violates this requirement.
4

Get reference images

Call: ViewImage (x2, in parallel)
Response:

Agent Response

RFI #___ Subject: Duct/Beam Conflict at Grid B-3, Level 2 Reference Drawings:
  • M-201: Mechanical Level 2 Plan (24x12 SA duct, CL EL 11’-0”)
  • S-201: Structural Level 2 Plan (W16x40 beam, T.O.S. 11’-2”, B.O.S. 9’-10”)
Description: The 24x12 supply air duct shown on M-201 at grid intersection B-3 conflicts with the W16x40 steel beam shown on S-201 at the same location. The duct bottom elevation (10’-6”) is 8” below the beam top elevation (11’-2”), creating a physical overlap. Per Mechanical General Note 1 on M-201, all ductwork shall maintain a minimum 2” clearance from structure. The current routing violates this requirement. Requested Action: Please advise on one of the following resolutions:
  1. Reroute the duct below the beam (requires minimum 9’-8” ceiling clearance confirmation)
  2. Provide a beam penetration detail if duct can pass through the web
  3. Resize the duct to fit above the beam flange

Summary